Two new roundabouts on Frank Road at Brown Road/Hardy Parkway Street and the separate Brown Road intersection are complete, the Franklin County Engineer’s Office announced Nov. 20.

The office described the completed project as improving traffic flow, safety and pedestrian connections. Its project updateidentifies two-lane roundabouts replacing the intersections’ previous traffic signals and stop controls.

The project followed a safety review documenting 56 crashes at the intersections from 2017 through 2019, including 21 injury crashes and one fatality, according to the county’s public-meeting materials. Those materials identified roundabouts as the recommended response to safety and congestion concerns.

The Franklin County Engineer’s Office and Ohio Department of Transportation held a public open house April 16, 2024. A handout prepared for that meeting listed an estimated construction cost of $9.2 million and $3.1 million in ODOT safety funding. Those figures reflect the earlier planning stage; the completion announcement did not provide a final cost.

The plans called for pavement reconstruction and widening on Frank Road, Brown Road and Hardy Parkway Street, along with lighting and drainage improvements. They also included shared-use paths south of Frank Road between the roundabouts and west of Brown Road north of Frank Road, plus sidewalks, curb ramps and other pedestrian facilities. The completion announcement did not separately itemize each finished feature.

In a response letter following the open house, Highway Design Engineer Matthew Rehfus summarized public concerns about large trucks, effects on businesses and properties, and traffic movement between the closely spaced roundabouts. Some commenters supported the project.

That letter tentatively scheduled construction to begin in spring 2026 and last approximately eight months. The Nov. 20 announcement confirms completion but does not specify the actual construction start or finish date.