Hilliard City Schools is preparing for a 2027 renovation of Davidson High School’s performing arts center while assessing athletic facilities and exterior doors for future improvements.
Those projects are the focus of the district’s November facilities update, posted Nov. 24, 2026. The attached presentation, dated Nov. 23, outlines upcoming work rather than providing new construction milestones for the district’s elementary school replacements.
The presentation schedules Davidson’s performing arts center renovation for April through November 2027. Contract approval is scheduled for the school board’s Dec. 14 meeting.
Planned work includes accessibility improvements, interior finishes, fire suppression, electrical systems, heating and cooling, and technology.
Athletic assessments cover the district’s three high schools and three middle schools. Architects will combine site evaluations with athletic directors’ feedback to help the district prioritize repairs and improvements. A separate exterior-door review assigns components a pass, repair or fail designation to guide future decisions.
Elementary projects and building moves
The broader Master Facilities Plan includes replacement buildings for Beacon, Brown and Ridgewood elementary schools, preschool expansion and conversion of the existing Brown building into a third sixth-grade school.
Beacon held its groundbreaking Feb. 9, 2026, according to the district’s February update. An Aug. 28 Rotary–Hilliard Connect recap described Beacon as under construction and reported extensive earthwork to prepare the site.
That recap also said construction of Brown’s replacement, on a 20-acre site north of the existing school, was expected to begin around Oct. 1. The November presentation does not establish whether that start occurred.
The existing Brown building will be repurposed as Wales Sixth Grade School, a name the district has since announced. The August recap described plans to relocate part of Station Sixth Grade there, move Hub programs into the resulting space at Station and temporarily house Ridgewood students at the Hub during replacement construction.
A new preschool facility at the Britton-Norwich Learning Campus is another Phase 1 project. Its construction should be distinguished from Ridgewood’s replacement.
Funding and longer-term plans
Voters approved a $142 million bond issue and a separate 6.9-mill operating levy in November 2024, according to the district’s facilities overview. The bond supports capital improvements; the operating levy supports district operations.
Rotary’s August report attributed to Superintendent Dave Stewart the statement that the bond was financed without additional millage. That description does not apply to the accompanying operating levy.
The same report placed Phase 1’s anticipated completion in spring 2030. It also described a potential future bond of approximately $155 million for additional needs, including Scioto Darby, Avery and J.W. Reason elementary schools.
Stewart’s projected six-year interval before another ballot request and anticipated elementary boundary changes around 2028 were planning estimates reported in August, rather than guarantees.
Earlier improvements include band towers completed at Bradley, Darby and Davidson high schools in May, according to the district’s May update. Its September update also listed playground, secured-entry and tennis-court projects among summer work, without confirming completion of every item.