Voters across Ohio rejected data center developments in nearly every community where the question appeared on the Nov. 3 ballot, with 10 communities approving outright bans and several more passing other restrictions.

21 Ohio ballot measures put data center measures before voters, the Ohio Capital Journal reported. In nearly every result, voters backed new restrictions or declined to approve measures that would have allowed construction. Ohio hosted the largest share of data center ballot fights in the country, Axios reported.

Ohio communities that banned large data centers

Ten cities approved charter amendments prohibiting large-scale data center construction, according to 614Now. All results reflect 100% of precincts reporting where that status is available.

Community

County

Yes vote

Granville

Licking

82.45%

Trenton

Butler

79.68%

Sunbury

Delaware

78.64%

Urbana

Champaign

77.25%

Upper Sandusky

Wyandot

76.92%

Pataskala

Licking

73.62%

Piqua

Miami

66.70%

Defiance

Defiance

64.73%

Conneaut

Ashtabula

64.18%

Oregon

Lucas

60.69%

Other Ohio data center measures

Several communities voted on proposals short of outright bans.

In Grove City (Franklin County), voters approved Issue 28 by 54.6% with all 30 precincts reporting, according to 10TV. The charter change requires voter approval for any development project that takes up 50 or more acres, uses more than 20 megawatts of electricity at peak capacity or consumes more than 500,000 gallons of water per day.

In Ashville (Pickaway County), 81.61% of voters rejected a proposal from EdgeConneX to build two data center buildings, with all four precincts reporting, 10TV reported.

Nationally, 33 ballot measures to restrict data centers had passed or were leading as of late on Nov. 3, according to the tracking website Data Centers on the Ballot, the Ohio Capital Journal reported. Only one measure nationwide, in North Dakota, resulted in a win for data center supporters.

What it means for Hilliard

The results underscore a fight Hilliard knows well. The city exhausted its legal remedies in September when it withdrew its appeal challenging the Ohio EPA's permit for a 72.9-megawatt fuel cell facility at the Amazon Web Services data center campus on Scioto Darby Road.

AEP Ohio is constructing the facility, which uses 228 Bloom Energy fuel cell units to power the data center's electricity demands, according to the city's Sept. 15 announcement.

Hilliard City Council President Emily Cole said at the time that the withdrawal was not an endorsement of the project. Outside counsel advised the city that the legal grounds were narrow, and council concluded there was "no realistic path" to the outcome residents wanted through continued litigation, the Columbus Dispatch reported.

Under Ohio law, the Ohio Power Siting Board holds exclusive jurisdiction over electric generation facilities larger than 50 megawatts. AEP Ohio cited that provision when it withdrew its application to Hilliard's Planning and Zoning Commission in October 2025, according to the city's statement.

Norwich Township trustees voted unanimously on March 24 to send 12 letters to various entities requesting first-responder and community safeguards for the fuel cell facilities, according to township meeting minutes. Trustee Rothenberg said at that meeting that independent, third-party air quality monitoring should be required both inside and outside the facilities.

Cole said in September that the city plans to conduct air quality testing after the fuel cells become operational.

"We remain disappointed that residents and local governments have so little ability to review or influence major power generation projects proposed within their own communities," Cole said in the city's statement.