Hilliard City Council approved a $36.4 million capital improvement budget for 2027, setting aside $900,000 for the costliest nonroutine project in the city's five-year capital plan: a full reconstruction of Leap Road.
The vote was 7-0.
Council acted at its Monday, Nov. 9 meeting without discussion, having reviewed the spending plan at an Oct. 26 committee of the whole meeting, as The Columbus Dispatch reported.
The Leap Road Corridor Improvements Project is the most expensive nonroutine capital project in Hilliard's current five-year capital improvement plan. The city plans to spend more than $20 million on it through 2029, according to the Dispatch.
The 2027 allocation will fund continued design work and begin right-of-way acquisition, City Engineer Letty Schamp told council at the Oct. 26 meeting. The heaviest spending comes in fiscal year 2029, when the city plans to put about $18.6 million toward the project. That would account for roughly 43% of that year's capital budget.
The project stretches along Leap Road from Cemetery Road to Scioto Darby Road. Much of the existing infrastructure is more than 50 years old, and underground utilities beneath the roadway are even older, according to the city's project webpage. Sidewalks along the east side can flood or turn muddy after storms, and the flat roadway has drainage problems that affect drivers, pedestrians and cyclists.
"Our costs did go up considerably on this project; it's very complicated," Schamp said at the Oct. 26 meeting. She noted the water line replacement alone carries a price tag of about $2.5 million.
Plans call for replacing a culvert, all water services, curbs and drainage. The city also wants to add two mini-roundabouts, sidewalks, shared-use paths, street lighting and potentially a sanitary sewer, Schamp said.
The project began in 2022 as part of Hilliard's Pedestrian/Bicycle Mobility and Safety Program.
Funding sources
Hilliard has secured $6.7 million from the Central Ohio Transit Authority's (COTA) LinkUS Transit Supportive Infrastructure program, a voter-supported capital fund. The city also intends to seek additional money from the Ohio Public Works Commission (OPWC), according to the city's project webpage. The remaining balance would come from city funds.
The city's project webpage lists the overall cost estimate at $9.5 million to $10.5 million. The Dispatch reported the five-year capital plan puts total spending at more than $20 million through 2029. The reason for the difference is not explained in either source.
What residents along the corridor should know
Construction will happen in phases over multiple seasons starting in 2029. Some temporary street closures will be needed, and the city plans to announce detours in advance. Driveway access will stay open except during short closures for driveway work.
Property owners along the corridor may be asked for small strips of right-of-way or temporary construction easements. Those details will not be determined until 2027, and the city said it will contact affected owners individually.